    Extending Contracts

     

    Hi

    If, on completion of an RFT document ( EU threshold), there was a provison put in place that the contracting authority may extend the contract for a further term on completion the project, does that fully cover the Contracting Authortiy from having to go to tender again?  The wording is   "option for renewal for another year should the CA decide to repeat the initiative again in 2009".  The new contract (which would obviously be with the same vendor again) would be almost the same as the last except for some small modifications which are due to the CA now understanding exactly want it needs for the project. 

    Bearing this in mind, can anyone confirm for me that it is okay to proceed with the same vendor again without going to the market again?

    Thank you

    Colm

  • 12-09-2008 15:07 In reply to

    • Shane Hogan
    • Top 10 Contributor
    • Joined on 08-18-2008
    • National Disablity Authority
    • Posts 3

    Re: Extending Contracts

    I wouldn't claim to be an expert on these matters. I was advised (by a source who knows a thing or two about these issues), that once the provision for extension of the contract was included in the original tender AND the price remains the same for the extended contract, there is no need to retender.

    Hope this helps.

     

    Shane

    Shane Hogan
    Project Manager - Excellence through Accessibility
    National Disability Authority

    Email: shogan@nda.ie
    Web: http://www.nda.ie/eta
    Direct Line: 01-6080497

  • 12-18-2008 15:39 In reply to

    • Liz Nolan
    • Top 10 Contributor
      Female
    • Joined on 08-22-2008
    • Department of Finance, NPPPU, Hatch St.
    • Posts 18

    Re: Extending Contracts

    If the possibility of extending the contract was made clear at the time of going to tender, and the cost of the service for the intended extended period included in the cost estimation, there should not be a problem.

    Billy Noone

    National Public Procurement Policy Unit
    Department of Finance
    Dublin 2

    Phone : + 353 1 639 6216
    email  : billy.noone@finance.gov.ie

     